An Estimate of the cost of the Rotunda as far as the contracts that have been made towards the completion of it go.

Amt Paid for Materials for the brick work $6905.47
 “p ⅌ Thorn & Chamberlain for the work— 2856.25   9,761.72
  To complete the brick work of the Lbrary & Terras  Say 1,000.00
Amt Contract with G. Raggi for 10 Bases & 2 Pilaster bases } 715.00
Cost of Capetels in Italy  Say 7000.00
Transportation, duty &c on the same & bases— 2450.00 10,165.00
pd for stone Window & doorsills 255.00
to complete the stone steps on the back & Terras Stonework 1200.00 1,455.00
paid for Materials principally Lumber & iron which nearly pays for all the Lumber 6,165.00
For Tin & Copper for the roof of Dome & Portico 2,000.00
Glass & Glazing including the skylight 500.00
$31,046.72
Nails, hard ware, painting & Workman’s bills will not I presume exceed the balance of the $41,000
respectfully submitted by your obt sert

A. S. Brockenbrough P.